Customer challenges
  • Our customer was developing a carbon storage hub consisting of two CO₂ injection wells
  • A perforate and squeeze job was performed on an outer surface casing on one of the wells, which needed remediation before the next section was drilled and the intermediate casing was run in hole
  • To re-instate and ensure longterm well integrity, a solution was required to isolate the perforated section of casing
Expro Excellence
  • A 46m 10.75” ReLine HYD System was run into the 13.375” casing across the perforated interval and expanded using the running tool
  • The post expanded ID of the liner was 11.798” and a successful pressure test was performed to 3,000psi
  • Expro collaborated with all parties involved on the installation to ensure a safe and successful operation
  • The installation was completed as planned due to thorough pre-job preparation and delivery
Value to client
  • The perforated section of the casing was successfully isolated, enabling our customer to drill and case deeper sections of the well
  • The large optimized post expanded ID of 11.798” ensured smooth passage of the subsequent drill ahead BHA and casing string
  • The successful installation allowed the operator to continue using the original wellbore instead of drilling a new CO₂ injector well
  • The ReLine HYD system solved two of the key challenges when developing CO₂ storage hubs
  • Cost reductions and operational efficiency
  • Ensuring long-term well integrity
Contact

ReLine HYD expandable liner provides well integrity solution on CO₂ injector well

In Brief
Supporting CCS operations with expandable liner
Product Line
  • Carbon Capture Utilization and Storage (CCUS)
Region
North and Latin America
Customer challenges
  • Our customer was developing a carbon storage hub consisting of two CO₂ injection wells
  • A perforate and squeeze job was performed on an outer surface casing on one of the wells, which needed remediation before the next section was drilled and the intermediate casing was run in hole
  • To re-instate and ensure longterm well integrity, a solution was required to isolate the perforated section of casing
Expro Excellence
  • A 46m 10.75” ReLine HYD System was run into the 13.375” casing across the perforated interval and expanded using the running tool
  • The post expanded ID of the liner was 11.798” and a successful pressure test was performed to 3,000psi
  • Expro collaborated with all parties involved on the installation to ensure a safe and successful operation
  • The installation was completed as planned due to thorough pre-job preparation and delivery
Value to client
  • The perforated section of the casing was successfully isolated, enabling our customer to drill and case deeper sections of the well
  • The large optimized post expanded ID of 11.798” ensured smooth passage of the subsequent drill ahead BHA and casing string
  • The successful installation allowed the operator to continue using the original wellbore instead of drilling a new CO₂ injector well
  • The ReLine HYD system solved two of the key challenges when developing CO₂ storage hubs
  • Cost reductions and operational efficiency
  • Ensuring long-term well integrity