Anonymous – ArticuLock
Customer challenges
  • The client was sailing the rig with 36” x 30” conductor string suspended beneath with a limited weather window, requiring a tool to stabilize the conductor string
Expro Excellence
  • ArticuLock® was used to de-couple the fixed MODU from the hanging conductor, enabling moving the rig up to 4.5m Hs
Value to client
  • The 100 MT conductor was suspended beneath ArticuLock® for 34 hours during rig transit at up to 1.5 knots
  • An allowable weather window for sailing the rig with conductor suspended underneath ArticuLock® successfully opened up to 4.5m Hs wave height
  • Removed the risk of harsh weather impacting rig move
Contact

Anonymous – ArticuLock

In Brief
Expro’s ArticuLock® enables safe suspension of tubulars during rig transit
Product Line
  • Frank’s Tubular Running Services (TRS)
  • Well Construction
Region
Europe and Sub Saharan Africa
Customer challenges
  • The client was sailing the rig with 36” x 30” conductor string suspended beneath with a limited weather window, requiring a tool to stabilize the conductor string
Expro Excellence
  • ArticuLock® was used to de-couple the fixed MODU from the hanging conductor, enabling moving the rig up to 4.5m Hs
Value to client
  • The 100 MT conductor was suspended beneath ArticuLock® for 34 hours during rig transit at up to 1.5 knots
  • An allowable weather window for sailing the rig with conductor suspended underneath ArticuLock® successfully opened up to 4.5m Hs wave height
  • Removed the risk of harsh weather impacting rig move