Expro Excellence
Production Solutions
Accelerated Production Solution provided customer with early cash to finance long term project
Customer challenges
  • An independent operator in West Africa needed to generate early cash to fund investment in its long-term production facilities
  • The Regulatory body requested well performance data before authorizing the start of commercial production
  • The temporary facility was to be operated and maintained until the permanent process facility was installed and commissioned
  • The safety challenges associated with SIMOPS – i.e. installation of the permanent facility whilst continuing to produce hydrocarbons via the temporary facility
  • Remote location: Difficult terrain to access the site and then install equipment
Expro Excellence
  • Expro mobilized and installed a well testing package that was configured such that additional equipment could be tied-in to continue production at increased rates of up to 10,000 bpd once the well test was complete
  • Production commenced with a single train of standard well test equipment and was subsequently increased with the addition of a second train installed in parallel
  • Stabilized crude oil was transferred into the client’s tank farm, from where it was finally exported to an FSO moored offshore
  • Although the site was not easily accessible and represented a logistical challenge the in-country team and Expro’s logistics resources ensured a scheduled and safe delivery of the facilities
  • The Expro central Production Solutions Product line together with the Expro Nigeria team managed the complete scope from contract award with engineering design, procurement, logistics, installation, commissioning, and start-up
Value to client
  • Installation of the temporary equipment was engineered such that it would not hinder the preparation of foundations and installation of the permanent facility; thereby providing excellent safety performance during SIMOPs
  • The piping between the process equipment and production manifold was engineered and designed to minimize the suspension of production when switching from the temporary equipment to the permanent facility; thereby, optimizing uptime, and maximizing production and cash flow for the client
  • Expro team provided the O&M services during the initial operation phase of the permanent facility and trained the client’s staff until they took over the operation of the plant
  • Zero unplanned shut down, resulting in 100% uptime during operation by Expro team
Contact

Accelerated Production Solution provided customer with early cash to finance long term project

In Brief
Expro mobilized and installed a well testing package that was configured such that additional equipment could be tied-in to continue production at increased rates of up to 10,000 bpd once the well test was complete
Product Line
  • Production Solutions
Region
Europe and Sub Saharan Africa
Customer challenges
  • An independent operator in West Africa needed to generate early cash to fund investment in its long-term production facilities
  • The Regulatory body requested well performance data before authorizing the start of commercial production
  • The temporary facility was to be operated and maintained until the permanent process facility was installed and commissioned
  • The safety challenges associated with SIMOPS – i.e. installation of the permanent facility whilst continuing to produce hydrocarbons via the temporary facility
  • Remote location: Difficult terrain to access the site and then install equipment
Expro Excellence
  • Expro mobilized and installed a well testing package that was configured such that additional equipment could be tied-in to continue production at increased rates of up to 10,000 bpd once the well test was complete
  • Production commenced with a single train of standard well test equipment and was subsequently increased with the addition of a second train installed in parallel
  • Stabilized crude oil was transferred into the client’s tank farm, from where it was finally exported to an FSO moored offshore
  • Although the site was not easily accessible and represented a logistical challenge the in-country team and Expro’s logistics resources ensured a scheduled and safe delivery of the facilities
  • The Expro central Production Solutions Product line together with the Expro Nigeria team managed the complete scope from contract award with engineering design, procurement, logistics, installation, commissioning, and start-up
Value to client
  • Installation of the temporary equipment was engineered such that it would not hinder the preparation of foundations and installation of the permanent facility; thereby providing excellent safety performance during SIMOPs
  • The piping between the process equipment and production manifold was engineered and designed to minimize the suspension of production when switching from the temporary equipment to the permanent facility; thereby, optimizing uptime, and maximizing production and cash flow for the client
  • Expro team provided the O&M services during the initial operation phase of the permanent facility and trained the client’s staff until they took over the operation of the plant
  • Zero unplanned shut down, resulting in 100% uptime during operation by Expro team
Contact

For further information, please contact:

production@expro.com